Instructions for use of the product
1. Installation: Check the size of the anchor bolt hole and correct it; hoist the mainframe and motor to the foundation respectively, adjust the vertical and pulley level, and fix the feed hopper; after the second grouting solidification, accurately adjust the pulley level and tighten the triangular belt; before installing the hopper, unscrew the bottom bolt of the bearing seat and install the "U" oil drain pipe; electricity The machine needs to be well grounded.
2. Test operation of the empty car: check the tightness of the bolt, add lubricating oil, manually move the pulley to confirm that there is no impact sound; start the power and irdle for 0.5-1 hours, and after the shutdown is fully checked for any abnormalities, the load operation can be carried out (mainly clockwise rotation, reverse is also possible).
3. Load operation: After 24 hours of load operation, start the machine and fasten all the bolts, and deal with abnormalities found in production in time.